01 Jul 2009
|
|
Tags:
|
Project news
|
Goonyella Blackwater Moura Newlands
|
Coal
|
09 Dec 2008
|
|
While the recent rain has certainly been very welcome, it has caused some havoc with construction. However we are still expecting completion in late 2005.
Tags:
|
Project news
|
-
|
-
|
28 Nov 2008
|
|
Abigroup is now in the final stages of earthworks and bridge construction, with most of the team expecting to be leaving the site from mid June, according to Jim Barry, Abigroup’s Project Director.
Tags:
|
Project news
|
-
|
-
|
28 Nov 2008
|
|
Construction of the Bauhinia Regional Rail Project in Central Queensland, the longest rail line to be built in the State since the mid 1980, has reached the half way point.
Tags:
|
Project news
|
-
|
-
|
28 Nov 2008
|
|
Construction of the Bauhinia Regional Rail Project is progressing well in central Queensland with more than 70 percent of bulk earthworks completed on the 110km line.
Tags:
|
Project news
|
-
|
-
|
28 Nov 2008
|
|
In May this year, Minister for Transport and Main Roads Paul Lucas launched QR’s $3.5 billion coal rail program including rail infrastructure projects, fleet upgrades and additions for Queensland’s coalindustry over the next five years.
Tags:
|
Project news
|
Blackwater
|
Coal
|
28 Nov 2008
|
|
The Blackwater System Enhancement Program (BSEP) incorporates a range of associated works to increase the capacity of the Blackwater system.
Tags:
|
Project news
|
-
|
-
|
28 Nov 2008
|
|
Construction of the extensive Bauhinia Regional Rail Project is ahead of schedule with the final track laid two months early completing the line from the new Rolleston Coal Mine to QR's Blackwater Coal System.
Tags:
|
Project news
|
-
|
-
|
28 Nov 2008
|
|
The dust monitoring schedule is progressing well with the second phase underway. The consultants now have monitoring equipment in the Goonyella system at Hay Point and Grass Tree.